Green line project tunneling lrt

Area: Tel Aviv

Project Value: TBD

Status: Ongoing

Israel

The green line project section G3.2 includes two TBM tunnels, three underground station outer-boxes, two portals, launching shafts, underpass, and open station at Lewinsky.
5.7 kilometer long tunnel dual lane using the TBM method of tunneling
The project is to construct infrastructure works for the constructing the tel aviv light rail
The works included relocation of wet & dry utilities, Slurry walls, structural steel works including struts & walers, construction of slab deck that include steel trusses & precast concrete slabs, excavation works for the underground stations, earth works & final landscaping that include asphaltm sidewalk & gardening

Contact us.


Email - info@oghandasa.com

Phone - +972-74-7015130


    Skip to toolbar